Drumquin battery storage plans rejected despite warning of costly appeal

Drumquin residents have secured a victory as battery storage plans for the hills around the village are rejected. SU558CD26 placeholder image
Drumquin residents have secured a victory as battery storage plans for the hills around the village are rejected. SU558CD26 | TC

Council could face substantial financial penalty if controversial development decision is overturned

Fermanagh and Omagh District Council has rejected plans for a controversial battery energy storage facility near Drumquin, despite a stark warning that the decision could leave ratepayers facing substantial financial costs if the developer successfully challenges the refusal.

In a closely contested vote, councillors voted five to four against the proposed battery energy storage system (BESS) on the Dooish Road, bringing a dramatic end to a planning application which has been the subject of fierce local opposition for almost two years.

The decision was taken despite the council's lead planning officer warning that a failure to provide sufficiently robust planning grounds for refusing permission could result in substantial costs being awarded against the local authority at appeal.

The proposal, submitted by Tetra Tech, attracted objections from almost 300 residents, with campaigners arguing that the development represented an unacceptable risk to the village and its surrounding community.

Amanda Braden, from the campaign group No More Windfarms in Drumquin, described the proposed facility as a ‘credible risk to the village’.

The decision followed heated exchanges at last Wednesday's planning committee meeting, where councillors heard competing arguments over community consultation, safety concerns and the cumulative impact of energy developments on the rural area.

However, it was the potential financial consequences of refusing the application which provided one of the most significant moments of the debate.

Council lead planning officer Paul McDermott warned members that they would need to be able to demonstrate clear and defensible planning reasons for their decision should Tetra Tech lodge an appeal.

“You will need a very rationalised approach in terms of planning context. If this goes to appeal and the council loses, then there is the risk that there will be substantial costs awarded against [the council] if we are not in a position to defend the reason or reasons for refusal,” he cautioned.

Despite that warning, councillors ultimately voted to reject the scheme.

The decision represents a significant victory for opponents of the development, who have repeatedly raised concerns about the implications of introducing another major energy-related facility into an area already affected by windfarm proposals.

DUP councillor Mark Buchanan questioned whether the equality needs of the local community had been properly considered, saying residents believed they already had more than their ‘fair share’ of wind energy developments.

He also highlighted the strength of feeling locally about the cumulative impact of such proposals.

Sinn Féin councillor Ann Marie Donnelly said her position on the BESS and associated windfarm applications had been misrepresented online, warning that the increasingly hostile commentary surrounding the proposals was creating an ‘incredibly negative’ impression of Drumquin.

“All development should happen with the community and not to the community. Many people are increasingly uncomfortable with the increasingly negative way in which the village is being portrayed,” she said.

“Drumquin is a thriving village but some of the commentary online has been deeply concerning. Unfortunately, this has created doubt about the planning process itself. The community must be reassured that all the community concerns have been given due consideration.”

Concerns over the consultation process also featured prominently.

Omagh town DUP councillor Errol Thompson said he was unhappy with the engagement undertaken by Tetra Tech, claiming that the company had failed to consult residents since the previous meeting four months ago.

“We are not happy with the consultation process,” he said.

Ms Braden told the committee that there had been ‘zero contact’ between the applicant and the campaign group since July 2026.

She said numerous requests for information had been submitted but there had been no meaningful engagement, with members instead being directed towards planning policies.

However, Tetra Tech representative Aidan Collins defended the company's approach, describing the consultation process as ‘rigorous’ and insisting that its doors were ‘always open’.

He said he had personally walked up and down the Dooish Road twice to speak with residents.

There was also disappointment that representatives from three key statutory bodies - the Northern Ireland Fire and Rescue Service, Northern Ireland Environment Agency and Health and Safety Executive - had declined invitations to attend the meeting.

All three organisations instead advised the council that their statutory responses, including information relating to an emergency response plan, addressed their respective responsibilities.

Omagh town Sinn Féin councillor Barry McElduff said he was disappointed that the organisations had not been represented in person, particularly given the opportunity for members to question the Fire Service.

He said there was ‘insufficient information’ available and that councillors had been particularly keen to hear directly from those responsible for emergency response arrangements.

The exchanges became so heated at one stage that the meeting was suspended following comments from the public gallery, while planning committee chairman, Thomas Maguire, repeatedly reminded attendees to respect the speaking arrangements.

Councillors subsequently entered a private session to discuss the legal implications of the application before returning to take the decisive vote.

With the five-to-four decision now made, the focus will turn to whether Tetra Tech challenges the refusal at appeal - and whether the council can successfully defend its position.

For the residents who have campaigned against the development, the vote represents an important moment in their fight to protect their community.

But the warning from the council's planning officer means the financial and legal consequences of the decision could yet have a significant bearing on the next chapter of the Drumquin dispute.